On measures related to the design and construction of the Barda-Agdam railway line” by Decree of the President of the Republic of Azerbaijan dated November 24, 2020 No. 2305 Design and construction of the Barda-Agdam railway line with a total length of 45 km


Customer: Closed Joint Stock Company “Azərbaycan Dəmir Yolları”
Type of infrastructure and work performed: Railway, design and new construction
Main scope of work:

  1. Axle length of the constructed road (km) – 47.1
  2. Length of dismantled road (km) – 17,514

Excavation:

  1. Vegetation layer – 92228 m3
  2. Excavations – 268928 m3
  3. Filling – 902154 m3
  4. Subballast – 74909 m3
  5. Ballast – 108988 m3
  6. Number of travelers – 34

Seris Road:

  1. Vegetation layer – 83966 m3
  2. Excavations – 15015 m3
  3. Filling – 288690 m3

Construction of stations:

  1. Tazakend
  2. Kocherli
  3. Barda

Duration of work (start and completion dates): 2020 (ongoing)