Construction of a 275 pm railway under the project “Design and reconstruction of the R-7 highway, Kh.Z. Tagiyev-Sumgayit for 4-lane traffic”


Customer: 17№-li Xüsusi Təyinatlı Yol İstismarı LLC
Type of infrastructure and work performed: Railway construction
Main scope of work:

  1. Length of paved road (pm) – 275 pm/road
  2. Ballast volume – 410 m3

Duration of work (start and completion dates): 2022