“Reconstruction of the existing bridge over the Kura River on the Alyat-Horadiz-Agband railway line and design and construction of a new bridge parallel to it” – construction of the 597 pm railway and installation of 11 sets of turnouts


Customer: Körpü-Bina-Tikinti LLC
Type of infrastructure and work covered by the work: Railway construction
Main scope of work:

  1. Length of paved road (lm) – 597 pm/road
  2. Ballast volume – 1194 m3
  3. Number of diverters – 11 sets

Duration of work (start and completion dates): 2022.